Local Case Studies
The local case studies for projects in different sectors were prepared to document the bottlenecks which occurred during the various processes involved in the life cycle of infrastructure projects. Identifying such processes allows a better underst...
Main Authors: | , , |
---|---|
Format: | Policy Note |
Language: | English en_US |
Published: |
World Bank, Washington, DC
2014
|
Subjects: | |
Online Access: | http://documents.worldbank.org/curated/en/2007/11/9368493/local-case-studies http://hdl.handle.net/10986/19543 |
id |
okr-10986-19543 |
---|---|
recordtype |
oai_dc |
spelling |
okr-10986-195432021-04-23T14:03:46Z Local Case Studies Abidi, Sohail Mir, Aized H. Durrani, Amer Z. AIRPORT AIRPORTS ARBITRATION BANK GUARANTEES BID BIDS BOTTLENECKS BREACH BRIDGE BUDGETING BUSINESS ENVIRONMENT BUSINESS RELATIONS BUYER BUYERS CAPACITY CONSTRAINTS CERTIFICATE CERTIFICATES CLAUSES COMMUNICATIONS TECHNOLOGY COMPETITIVE BIDDING CONTRACT ADMINISTRATION CONTRACT VALUE CONTRACTOR CONTRACTORS COST ESTIMATES COUNTRY OF ORIGIN COVENANT CREDIBILITY CURRENCY DEVELOPMENT BANK DEVELOPMENT BANKS DEVELOPMENT FINANCE DEVELOPMENT FINANCE COMPANIES DISCLOSURE DISPUTE RESOLUTION ELECTRICITY EMPLOYER EQUIPMENT EQUIPMENT PURCHASE EXCHANGE COMMISSION EXCHANGE RATES EXPATRIATE EXPENDITURES FINANCIAL CRISES FOREIGN EXCHANGE HIGHWAY HIGHWAY AUTHORITY HUMAN RESOURCE HUMAN RESOURCES ICT IMAGES IMPLEMENTATION PERIOD IMPLEMENTING AGENCIES IMPLEMENTING AGENCY INFRASTRUCTURE PROJECTS INSTALLMENTS INTERNATIONAL AIRPORT INTERNATIONAL BANK INTERNATIONAL COURT INTERNATIONAL DEVELOPMENT INTERNATIONAL FINANCE INTERNATIONAL STANDARDS ISLAMIC BANK JOINT VENTURE LANES LETTER OF CREDIT LOAN LOAN AGREEMENT LOAN AMOUNT LOAN COVENANTS LOCAL BANKS LOCAL CONTRACTORS MANAGEMENT SERVICES MATERIAL NEGOTIATIONS PC PHOTO PORT AUTHORITIES PROCUREMENT PROCUREMENT PROCEDURES PUBLIC PROCUREMENT RAIL RAIL LINK REGISTRY REGISTRY SYSTEM REGULATORY AUTHORITY REQUEST FOR PROPOSAL RESULT RESULTS ROAD SOVEREIGN GUARANTEES SUBCONTRACTORS TELECOMMUNICATION TENURE TERMINATION TIME PERIOD TRAFFIC TRAFFIC VOLUMES TRAINING CENTER TRANSPORT TRANSPORT AUTHORITY TRANSPORTATION TRANSPORTATION OFFICIALS TRUE VERIFICATION The local case studies for projects in different sectors were prepared to document the bottlenecks which occurred during the various processes involved in the life cycle of infrastructure projects. Identifying such processes allows a better understanding of the capacity constraints in planning, designing, programming, procurement, contract administration, financing and budgeting, execution, and other stages in a project cycle. The case studies clearly demonstrate the presence of deep rooted systematic problems related to: (1) inadequate client capacity to plan, procure, program, administer, and manage projects; (2) imbalanced conditions of contracts; (3) flawed procurement procedures (pre-qualification, bid evaluation, negotiations, and re-negotiations with the lowest bidder) causing significant delays; (4) mismatched project funding needs and actual availability of funds; (5) commencement of projects without ensuring that required funds are in place; (6) delay in making running payments; (7) insufficient time given for detailed design and variations in contract due to inadequacies in design; (8) limited capacity of local contractors; and (9) poor international bid response in mega projects related to credibility issues. 2014-08-20T21:31:51Z 2014-08-20T21:31:51Z 2007-11 http://documents.worldbank.org/curated/en/2007/11/9368493/local-case-studies http://hdl.handle.net/10986/19543 English en_US CC BY 3.0 IGO http://creativecommons.org/licenses/by/3.0/igo/ World Bank, Washington, DC Economic & Sector Work :: Policy Note Economic & Sector Work South Asia Pakistan |
repository_type |
Digital Repository |
institution_category |
Foreign Institution |
institution |
Digital Repositories |
building |
World Bank Open Knowledge Repository |
collection |
World Bank |
language |
English en_US |
topic |
AIRPORT AIRPORTS ARBITRATION BANK GUARANTEES BID BIDS BOTTLENECKS BREACH BRIDGE BUDGETING BUSINESS ENVIRONMENT BUSINESS RELATIONS BUYER BUYERS CAPACITY CONSTRAINTS CERTIFICATE CERTIFICATES CLAUSES COMMUNICATIONS TECHNOLOGY COMPETITIVE BIDDING CONTRACT ADMINISTRATION CONTRACT VALUE CONTRACTOR CONTRACTORS COST ESTIMATES COUNTRY OF ORIGIN COVENANT CREDIBILITY CURRENCY DEVELOPMENT BANK DEVELOPMENT BANKS DEVELOPMENT FINANCE DEVELOPMENT FINANCE COMPANIES DISCLOSURE DISPUTE RESOLUTION ELECTRICITY EMPLOYER EQUIPMENT EQUIPMENT PURCHASE EXCHANGE COMMISSION EXCHANGE RATES EXPATRIATE EXPENDITURES FINANCIAL CRISES FOREIGN EXCHANGE HIGHWAY HIGHWAY AUTHORITY HUMAN RESOURCE HUMAN RESOURCES ICT IMAGES IMPLEMENTATION PERIOD IMPLEMENTING AGENCIES IMPLEMENTING AGENCY INFRASTRUCTURE PROJECTS INSTALLMENTS INTERNATIONAL AIRPORT INTERNATIONAL BANK INTERNATIONAL COURT INTERNATIONAL DEVELOPMENT INTERNATIONAL FINANCE INTERNATIONAL STANDARDS ISLAMIC BANK JOINT VENTURE LANES LETTER OF CREDIT LOAN LOAN AGREEMENT LOAN AMOUNT LOAN COVENANTS LOCAL BANKS LOCAL CONTRACTORS MANAGEMENT SERVICES MATERIAL NEGOTIATIONS PC PHOTO PORT AUTHORITIES PROCUREMENT PROCUREMENT PROCEDURES PUBLIC PROCUREMENT RAIL RAIL LINK REGISTRY REGISTRY SYSTEM REGULATORY AUTHORITY REQUEST FOR PROPOSAL RESULT RESULTS ROAD SOVEREIGN GUARANTEES SUBCONTRACTORS TELECOMMUNICATION TENURE TERMINATION TIME PERIOD TRAFFIC TRAFFIC VOLUMES TRAINING CENTER TRANSPORT TRANSPORT AUTHORITY TRANSPORTATION TRANSPORTATION OFFICIALS TRUE VERIFICATION |
spellingShingle |
AIRPORT AIRPORTS ARBITRATION BANK GUARANTEES BID BIDS BOTTLENECKS BREACH BRIDGE BUDGETING BUSINESS ENVIRONMENT BUSINESS RELATIONS BUYER BUYERS CAPACITY CONSTRAINTS CERTIFICATE CERTIFICATES CLAUSES COMMUNICATIONS TECHNOLOGY COMPETITIVE BIDDING CONTRACT ADMINISTRATION CONTRACT VALUE CONTRACTOR CONTRACTORS COST ESTIMATES COUNTRY OF ORIGIN COVENANT CREDIBILITY CURRENCY DEVELOPMENT BANK DEVELOPMENT BANKS DEVELOPMENT FINANCE DEVELOPMENT FINANCE COMPANIES DISCLOSURE DISPUTE RESOLUTION ELECTRICITY EMPLOYER EQUIPMENT EQUIPMENT PURCHASE EXCHANGE COMMISSION EXCHANGE RATES EXPATRIATE EXPENDITURES FINANCIAL CRISES FOREIGN EXCHANGE HIGHWAY HIGHWAY AUTHORITY HUMAN RESOURCE HUMAN RESOURCES ICT IMAGES IMPLEMENTATION PERIOD IMPLEMENTING AGENCIES IMPLEMENTING AGENCY INFRASTRUCTURE PROJECTS INSTALLMENTS INTERNATIONAL AIRPORT INTERNATIONAL BANK INTERNATIONAL COURT INTERNATIONAL DEVELOPMENT INTERNATIONAL FINANCE INTERNATIONAL STANDARDS ISLAMIC BANK JOINT VENTURE LANES LETTER OF CREDIT LOAN LOAN AGREEMENT LOAN AMOUNT LOAN COVENANTS LOCAL BANKS LOCAL CONTRACTORS MANAGEMENT SERVICES MATERIAL NEGOTIATIONS PC PHOTO PORT AUTHORITIES PROCUREMENT PROCUREMENT PROCEDURES PUBLIC PROCUREMENT RAIL RAIL LINK REGISTRY REGISTRY SYSTEM REGULATORY AUTHORITY REQUEST FOR PROPOSAL RESULT RESULTS ROAD SOVEREIGN GUARANTEES SUBCONTRACTORS TELECOMMUNICATION TENURE TERMINATION TIME PERIOD TRAFFIC TRAFFIC VOLUMES TRAINING CENTER TRANSPORT TRANSPORT AUTHORITY TRANSPORTATION TRANSPORTATION OFFICIALS TRUE VERIFICATION Abidi, Sohail Mir, Aized H. Durrani, Amer Z. Local Case Studies |
geographic_facet |
South Asia Pakistan |
description |
The local case studies for projects in
different sectors were prepared to document the bottlenecks
which occurred during the various processes involved in the
life cycle of infrastructure projects. Identifying such
processes allows a better understanding of the capacity
constraints in planning, designing, programming,
procurement, contract administration, financing and
budgeting, execution, and other stages in a project cycle.
The case studies clearly demonstrate the presence of deep
rooted systematic problems related to: (1) inadequate client
capacity to plan, procure, program, administer, and manage
projects; (2) imbalanced conditions of contracts; (3) flawed
procurement procedures (pre-qualification, bid evaluation,
negotiations, and re-negotiations with the lowest bidder)
causing significant delays; (4) mismatched project funding
needs and actual availability of funds; (5) commencement of
projects without ensuring that required funds are in place;
(6) delay in making running payments; (7) insufficient time
given for detailed design and variations in contract due to
inadequacies in design; (8) limited capacity of local
contractors; and (9) poor international bid response in mega
projects related to credibility issues. |
format |
Economic & Sector Work :: Policy Note |
author |
Abidi, Sohail Mir, Aized H. Durrani, Amer Z. |
author_facet |
Abidi, Sohail Mir, Aized H. Durrani, Amer Z. |
author_sort |
Abidi, Sohail |
title |
Local Case Studies |
title_short |
Local Case Studies |
title_full |
Local Case Studies |
title_fullStr |
Local Case Studies |
title_full_unstemmed |
Local Case Studies |
title_sort |
local case studies |
publisher |
World Bank, Washington, DC |
publishDate |
2014 |
url |
http://documents.worldbank.org/curated/en/2007/11/9368493/local-case-studies http://hdl.handle.net/10986/19543 |
_version_ |
1764441358150402048 |